building progress

Berg Station Bohol retirement Village

December 2019
street development begin
site development begin
shortly for Christmas, street filling
not compressed due to holiday
2020 and the project goes on
street goes on and is temporary ready for drive in
January 2020
ground breaking for the Village
drilling the deep well (111 feet actual) and layout the first Villa
drilling the deep well (282 feet actual) strong water source found
foundation preparation for the first Villa
foundation filling for the first Villa
March 2020
first prime location Villa is raising in Berg Station retirement village
even in the covid-19 mass hysteria
recognize the nice view, more bushes will be cut in the future.
cleaning of deep well and more progress
April 2020
road rip rapping done
embankment of flooring
walls are raising
Prime location Villa gets more and more contour
May 2020
roof getting build
walls getting plastered and terrace roof under construction
getting more tidy insite
June 2020
the roof is build but not finished yet
the floor is done
July 2020
ceiling gets finished and tile work get done, power room / storage ready
tile work nearly done, texture on wall, first coat of paint done
August 2020
The windows are in
white aluminium frame, blue tinted reflective glass. magnetic fly screen.
September 2020
big changes coming up house get finish now
the house get an outside coat of white cement step 1
house painting in modern color step 2 in progress
October 2020
so many changes and updates happen no time for pictures but shortly come the final in November.....
for those who like to follow us on FB here is our link...
November 2020
our first house is ready and we like to present our show home for viewing and buying.